COMPLETION AND SETTLEMENT UPDATE

8TH NOVEMBER 2022

As we prepare for completion of Signature Broadbeach, the development team has been working closely with Icon and ULTIQA to provide you with your apartment as soon as possible.

Icon have reported making good progress on-site over the last month and if progress continues on program, we are expecting to call for settlement for the majority of the units in Levels 5-33 the week beginning 21st November 2022, with settlements to occur 14 days later.

We appreciate that this is a challenging time in the lead up to the Christmas break and understand you are keen to take possession of your new apartment as soon as possible. We are working very closely with Icon and we will advise you immediately should there be any material changes to these indicative settlement timeframes.

BUILDING MANAGER UPDATE

The Building Manager, ULTIQA will be in contact with owners over the coming weeks to introduce Scott Carlin, the on-site manager and provide further logistical information including details of Building Link, the building management platform that will be used to book a lift for your move-in once settlement occurs. Building Link is also used to book amenities such as the private dining room and the movie theatre.

For those purchasers who are entering into a management agreement with ULTIQA , there will be a further update provided in due course as to when your unit will be available for letting, based on furniture installations.

To ensure you are up to date through the completion and settlement phases of the development we will  begin to provide regular weekly updates to purchasers.  If you have any additional queries, please do not hesitate to contact your settlement manager or reach out via the Signature App.

Share

Related News

Signature Broadbeach Construction and settlement Update

21ST NOVEMBER 2022

We are pleased to report that over the past couple of weeks, Icon has made good progress with the following works currently being undertaken on-site.

Read More

COMPLETION AND SETTLEMENT UPDATE

12TH OCTOBER 2022

We are writing to provide an update on the impending completion and settlement of Signature Broadbeach.

Whilst our previous communications indicated a late October completion date, we unfortunately have recently been advised by Icon that there will be a slight delay in completion, and we are now expecting to call for settlements in mid November for Levels 5 – 33 and late November to early December for Levels 34 and 35.

Read More

SIGNATURE BROADBEACH UPDATE – AUGUST 2022

29TH AUGUST 2022

We are pleased to advise significant progress has been made over the past month with the removal of the tower crane and hoist (builders lift). Passenger lifts are now installed and operational, façade glazing complete and all levels up to 30 are fully plastered with joinery installed.

Read More