News

EVERYTHING THAT’S HAPPENING IN THE WORLD OF SIGNATURE

It’s a landmark for beachside living. Keep up with every step of the Signature Broadbeach story with news, media, insights and videos.

News

Signature Broadbeach Construction and settlement Update

21ST NOVEMBER 2022

We are pleased to report that over the past couple of weeks, Icon has made good progress with the following works currently being undertaken on-site.

Read More

COMPLETION AND SETTLEMENT UPDATE

8TH NOVEMBER 2022

As we prepare for completion of Signature Broadbeach, the development team has been working closely with Icon and ULTIQA to provide you with your apartment as soon as possible.

Icon have reported making good progress on-site over the last month and if progress continues on program, we are expecting to call for settlement for the majority of the units in Levels 5-33 the week beginning 21st November 2022, with settlements to occur 14 days later.

Read More

COMPLETION AND SETTLEMENT UPDATE

12TH OCTOBER 2022

We are writing to provide an update on the impending completion and settlement of Signature Broadbeach.

Whilst our previous communications indicated a late October completion date, we unfortunately have recently been advised by Icon that there will be a slight delay in completion, and we are now expecting to call for settlements in mid November for Levels 5 – 33 and late November to early December for Levels 34 and 35.

Read More

Signature Broadbeach settlement pack out now

12TH SEPTEMBER 2022

This is an exciting time in your home buying journey, and we understand it can also be a confusing one, especially if you are new to purchasing of the plan.  To ensure you understand the settlement process we have put together a comprehensive Settlement Pack which you can download via the link below.

Read More

SIGNATURE BROADBEACH UPDATE – AUGUST 2022

29TH AUGUST 2022

We are pleased to advise significant progress has been made over the past month with the removal of the tower crane and hoist (builders lift). Passenger lifts are now installed and operational, façade glazing complete and all levels up to 30 are fully plastered with joinery installed.

Read More

Signature Broadbeach App and Portal is now live!

22ND AUGUST 2022

We are very excited to announce the Signature Broadbeach App and Portal is now live.

This App will be used as a communication and documentation hub allowing you direct access to your important purchase documents and information as well as instant communication via direct messaging with your settlement agents David Crompton, Cameron Kohring and Faddy Fan.

Read More

SIGNATURE BROADBEACH UPDATE – JULY 2022

22ND JULY 2022

We have maintained good productivity on site throughout June with the final piece of structure being placed on the rooftop and the dismantling of the crane to be completed by the end of the week. These are both significant milestones as we move towards completion.

Passenger lifts have now been installed to level 35, facade glazing is complete to level 34 and all levels up to level 26 are fully plastered with joinery installed.

Read More

Signature Broadbeach Update – June 2022

16TH JUNE 2022

We are happy to report that the rain has eased and construction has progressed well in the past month with passenger lifts installed to level 30, facade glazing complete to level 32 and all levels up to level 28 fully plastered and joinery installed.

Read More

Signature Broadbeach Update – May 2022

20TH MAY 2022

We are very pleased to advise that Signature Broadbeach has now officially ‘topped out’, meaning that the roof of the building has been fully constructed. This is a significant milestone in the project and one that moves us into the final stage of construction being the ongoing fit out of apartments and common areas. We have already made significant progress on the internal fit out, with all levels up to level 21 fully plastered and joinery installed.

Read More