Construction Update – September 2019

24TH SEPTEMBER 2019

As we move into spring, construction activity continues on site at Signature with the builders busy installing pile foundations. These are deep concrete columns within the ground which provide the base for Signature’s structure. 37 pile foundations are now complete, constructed to depths of 50 metres below ground.

Construction of the basement perimeter ”diaphragm wall” will commence this week, and the basement perimeter guide wall installation is complete.

Specialised ground anchors, which will be installed to the diaphragm wall during basement excavation, have been ordered and are on their way to Broadbeach from Germany.

Completion at Signature is anticipated for the first half of 2022.

__

FEATURE APARTMENT

An unrivalled investment opportunity – achieve a return of over 6%*

APARTMENT 2103
2 bedroom | 2 bathroom | 1 car
$832,500
Click to view floor plan
To enquire, contact Natasha Pezet on 07 4408 0999 or npezet@kmsm.com.au.

__

CONSTRUCTION TIMELAPSE

View a snapshot of recent activity on site with the Signature construction timelapse video here.

 

Share

Related News

Signature Broadbeach settlement pack out now

12TH SEPTEMBER 2022

This is an exciting time in your home buying journey, and we understand it can also be a confusing one, especially if you are new to purchasing of the plan.  To ensure you understand the settlement process we have put together a comprehensive Settlement Pack which you can download via the link below.

Read More

Signature Broadbeach Update - June 2022

16TH JUNE 2022

We are happy to report that the rain has eased and construction has progressed well in the past month with passenger lifts installed to level 30, facade glazing complete to level 32 and all levels up to level 28 fully plastered and joinery installed.

Read More

Signature Broadbeach Update - May 2022

20TH MAY 2022

We are very pleased to advise that Signature Broadbeach has now officially ‘topped out’, meaning that the roof of the building has been fully constructed. This is a significant milestone in the project and one that moves us into the final stage of construction being the ongoing fit out of apartments and common areas. We have already made significant progress on the internal fit out, with all levels up to level 21 fully plastered and joinery installed.

Read More