Construction Update – November 2019

19TH NOVEMBER 2019

It’s been a huge year at Signature Broadbeach with the end of 2019 fast approaching. Following the commencement of construction earlier in the year, the builders have made excellent progress on site.

Installation of bored foundation piles is now complete. The diaphragm wall installation to the perimeter of the building basement is currently underway and should be completed in December – this wall is the building’s basement retention system.

In the next month, services will be connected to the site, and the capping beam will be installed to the top of the retention wall.

In a significant milestone for the project, excavation of the basement is set to commence prior to the end of the year.

Completion at Signature is anticipated for the first half of 2022.

ONGOING COMMUNICATION

We will continue to communicate with you regularly as we move through the construction journey.

All Project News updates are available on the Signature Broadbeach website.

If you have an email which you would like to receive these updates, please notify us at settlements@littleprojects.com.au

Share

Related News

Signature Broadbeach settlement pack out now

12TH SEPTEMBER 2022

This is an exciting time in your home buying journey, and we understand it can also be a confusing one, especially if you are new to purchasing of the plan.  To ensure you understand the settlement process we have put together a comprehensive Settlement Pack which you can download via the link below.

Read More

Signature Broadbeach Update - June 2022

16TH JUNE 2022

We are happy to report that the rain has eased and construction has progressed well in the past month with passenger lifts installed to level 30, facade glazing complete to level 32 and all levels up to level 28 fully plastered and joinery installed.

Read More

Signature Broadbeach Update - May 2022

20TH MAY 2022

We are very pleased to advise that Signature Broadbeach has now officially ‘topped out’, meaning that the roof of the building has been fully constructed. This is a significant milestone in the project and one that moves us into the final stage of construction being the ongoing fit out of apartments and common areas. We have already made significant progress on the internal fit out, with all levels up to level 21 fully plastered and joinery installed.

Read More