Program Update – March 2022

2ND MARCH 2022

Following on from our February Construction Update which was based on available information and advice at the time, we have recently been informed that there has been a change to the project completion timeline.

Whilst we are extremely pleased with the quality and overall progress of the Signature Broadbeach project, unfortunately we must inform you that following a recent review, ICON Constructions (builder) has advised the Construction Program has been delayed.

The revised anticipated completion of Signature Broadbeach will be 3rd quarter of 2022. This delay is due to a combination of COVID-19 impacts (including reduced labour due to illness, supply issues and State Government Orders), and poor weather conditions over the past 2-3 months.

We are working very closely with ICON to try to minimise the delay and apologise for any inconvenience caused. We assure you the team is doing everything they can to deliver your apartment as quickly as possible and to the highest quality.

On a positive note, ICON has advised that the Concrete Structure will ‘top off’ / complete in the coming weeks with the tower crane to come down in the weeks following. This is a significant milestone for the Project as we move into the final stages.

To ensure you are fully informed throughout the remainder of the project and can prepare for settlement, we will continue to communicate with you regularly. There will also be information regarding letting opportunities, furniture packages and blind/curtain packages which will be communicated soon.

We once again apologise for the delay and for any inconvenience this has caused.

If you have any additional queries, please do not hesitate to contact us at settlements@kmdevelop.com

 

SIGNATUREBROADBEACH.COM.AU

Share

Related News

Signature Broadbeach settlement pack out now

12TH SEPTEMBER 2022

This is an exciting time in your home buying journey, and we understand it can also be a confusing one, especially if you are new to purchasing of the plan.  To ensure you understand the settlement process we have put together a comprehensive Settlement Pack which you can download via the link below.

Read More

Signature Broadbeach Update - June 2022

16TH JUNE 2022

We are happy to report that the rain has eased and construction has progressed well in the past month with passenger lifts installed to level 30, facade glazing complete to level 32 and all levels up to level 28 fully plastered and joinery installed.

Read More

Signature Broadbeach Update - May 2022

20TH MAY 2022

We are very pleased to advise that Signature Broadbeach has now officially ‘topped out’, meaning that the roof of the building has been fully constructed. This is a significant milestone in the project and one that moves us into the final stage of construction being the ongoing fit out of apartments and common areas. We have already made significant progress on the internal fit out, with all levels up to level 21 fully plastered and joinery installed.

Read More